bammie schreef op 10 oktober 2014 14:22:
@KOS
Wat denk jij van onderstaande claim mbt vetgedrukte?
It is estimated the latest repairs could take three years to complete.BAM was two years late in handing over the project and claimed the council owed them around £70m more than the £84m contract price, triggering a protracted legal dispute.
The contractor said the busway had cost it £152m to build and claimed it should receive an extra £43m on top of the £118m the authority had already paid them.
But in August 2013 after an on-going legal battle over the late delivery of the project, BAM agreed to pay back £33m bringing the price paid by the council back to the original contract value.
If the council succeeds in its latest claim the total project cost would rise to around £183m.BAM Nuttall would not comment on the matter.
Bron:
www.constructionenquirer.com/2014/10/...