Our guidance calls for 100 megawatt in operations by end of this year, and we are on track to deal with that. Also, I would like to highlight that, all these new facilities are potentially scalable to a total of more than 300 megawatts as and when we are ready to do so. We are working on even further expansion, focusing on greenfield sites in U. S. And Europe that would increase our capacity, multiply times.
And I think during that conversation, I talked about a potential to building a gigawatt and more of capacity if we see that the demand is there. And I still believe that the advantage of having a team like ours, which with decades of experience of building hundreds of megawatts of data centers in a specific products gives us this advantage. And as Andre said, we already have over 300 megawatts secured and we know how to scale it well, well, much more above that.